1 |
MINISTRY OF WORKS AND TRANSPORT |
|
ocds-xwwr9a |
|
|
|
|
|
|
2025-01-16T12:50:08 |
|
|
2 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE I) |
ocds-xwwr9a |
ocds-xwwr9a-045007-OS/WT/01-NG045009 |
72141000 |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE I) |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE I) |
8,916,334,484.62 |
2025 |
2025-04-28T15:24:39 |
2025-05-19T12:00 |
2025-05-21T08:00 |
3 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF OKE GADA - ADELEKE UNIVERSITY HIGH SCHOOL EDE. PHASE I |
ocds-xwwr9a |
ocds-xwwr9a-045010-OS/WT/01-NG045012 |
72141000 |
DUALIZATION OF OKE GADA - ADELEKE UNIVERSITY HIGH SCHOOL EDE. PHASE I |
DUALIZATION OF OKE GADA - ADELEKE UNIVERSITY HIGH SCHOOL EDE. PHASE I |
9,928,670,072.3 |
2025 |
2025-04-17T13:00:40 |
2025-05-19T12:00 |
2025-05-21T08:00 |
4 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF ADELEKE UNIVERSITY HIGH SCHOOL -AIR FORCE AREA IDO OSUN. PHASE II |
ocds-xwwr9a |
ocds-xwwr9a-045073-OS/WT/01-NG045075 |
72141000 |
DUALIZATION OF ADELEKE UNIVERSITY HIGH SCHOOL -AIR FORCE AREA IDO OSUN. PHASE II |
DUALIZATION OF ADELEKE UNIVERSITY HIGH SCHOOL -AIR FORCE AREA IDO OSUN. PHASE II |
9,651,539,600.01 |
2025 |
2025-04-28T16:37:26 |
2025-05-19T12:00 |
2025-05-21T08:00 |
5 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF AIR FORCE AREA TO OFFATEDO JUNCTION. PHASE III |
ocds-xwwr9a |
ocds-xwwr9a-045136-OS/WT/01-NG045138 |
72141000 |
DUALIZATION OF AIR FORCE AREA TO OFFATEDO JUNCTION. PHASE III |
DUALIZATION OF AIR FORCE AREA TO OFFATEDO JUNCTION. PHASE III |
8,950,493,521.53 |
2025 |
2025-04-17T10:27:39 |
2025-05-19T12:00 |
2025-05-21T08:00 |
6 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF OKE GADA TO ORITA AWO JUNCTION EDE |
ocds-xwwr9a |
ocds-xwwr9a-045202-OS/WT/01-NG045204 |
72141000 |
DUALIZATION OF OKE GADA TO ORITA AWO JUNCTION EDE |
DUALIZATION OF OKE GADA TO ORITA AWO JUNCTION EDE |
9,611,948,405.2 |
2025 |
2025-04-28T16:35:28 |
2025-05-19T01:10 |
2025-05-21T08:00 |
7 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF MUSLIM BURIAL GROUND-YTD, OJORO ROAD, EDE (PHASE III) |
ocds-xwwr9a |
ocds-xwwr9a-045355-OS/WT/01-NG045357 |
72141000 |
DUALIZATION OF MUSLIM BURIAL GROUND-YTD, OJORO ROAD, EDE (PHASE III) |
DUALIZATION OF MUSLIM BURIAL GROUND-YTD, OJORO ROAD, EDE (PHASE III) |
2,548,867,968.04 |
2025 |
2025-04-28T16:04:06 |
2025-05-19T12:00 |
2025-05-21T08:00 |
8 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE 2) |
ocds-xwwr9a |
ocds-xwwr9a-046579-OS/WT/01-NG046581 |
72141000 |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE 2) |
DUALIZATION OF ABEERE ROUNDABOUT - YTD OJORO ROAD, EDE (PHASE 2) |
9,839,077,591.97 |
2025 |
2025-04-28T16:59:08 |
2025-05-19T12:00 |
2025-05-21T08:00 |
9 |
MINISTRY OF WORKS AND TRANSPORT |
REHABILITATION OF EJIGBO - IWO ROAD (IWATA-ILAWO BOUNDARY) PHASE 2 |
ocds-xwwr9a |
ocds-xwwr9a-046904-OS/WT/01-NG046906 |
72141000 |
REHABILITATION OF EJIGBO - IWO ROAD (IWATA-ILAWO BOUNDARY) PHASE 2 |
REHABILITATION OF EJIGBO - IWO ROAD (IWATA-ILAWO BOUNDARY) PHASE 2 |
2,372,480,189.16 |
2025 |
2025-04-17T12:00:40 |
2025-05-19T12:00 |
2025-05-21T08:00 |
10 |
MINISTRY OF WORKS AND TRANSPORT |
REHABILITATION OF EJIGBO - IWO (EJIGBO-IWATA BOUNDARY), PHASE 1 |
ocds-xwwr9a |
ocds-xwwr9a-047041-OS/WT/01-NG047043 |
72141000 |
Selective tendering |
REHABILITATION OF EJIGBO - IWO (EJIGBO-IWATA BOUNDARY), PHASE 1 |
3,200,660,328.13 |
2025 |
2025-04-17T12:00:20 |
2025-05-19T12:00 |
2025-05-21T08:00 |
11 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF OWODE EDE MARKET - AKANKAN Y-JUNCTION,EDE |
ocds-xwwr9a |
ocds-xwwr9a-047105-OS/WT/01-NG047107 |
72141000 |
DUALIZATION OF OWODE EDE MARKET - AKANKAN Y-JUNCTION,EDE |
DUALIZATION OF OWODE EDE MARKET - AKANKAN Y-JUNCTION,EDE |
10,692,791,662.99 |
2025 |
2025-04-17T12:12:29 |
2025-05-19T12:00 |
2025-05-21T08:00 |
12 |
MINISTRY OF WORKS AND TRANSPORT |
DUALIZATION OF ROAD FROM ODO - ORI JUNCTION - POST OFFICE JUNCTION ROAD WITH SPUR TO OLUWO PALACE, IWO |
ocds-xwwr9a |
ocds-xwwr9a-047180-OS/WT/01-NG047182 |
72141000 |
DUALIZATION OF ROAD FROM ODO - ORI JUNCTION - POST OFFICE JUNCTION ROAD WITH SPUR TO OLUWO PALACE, IWO |
DUALIZATION OF ROAD FROM ODO - ORI JUNCTION - POST OFFICE JUNCTION ROAD WITH SPUR TO OLUWO PALACE, IWO |
9,782,595,083.99 |
2025 |
2025-04-28T16:07:31 |
2025-05-19T12:00 |
2025-05-21T08:00 |
13 |
MINISTRY OF WORKS AND TRANSPORT |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD, PHASE 2 |
ocds-xwwr9a |
ocds-xwwr9a-047764-OS/WT/01-NG047766 |
72141000 |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD, PHASE 2 |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD, PHASE 2 |
1,685,330,760.22 |
2025 |
2025-04-17T12:00:39 |
2025-05-19T12:00 |
2025-05-21T08:00 |
14 |
MINISTRY OF WORKS AND TRANSPORT |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD (PHASE 1) |
ocds-xwwr9a |
ocds-xwwr9a-047871-OS/WT/01-NG047873 |
72141000 |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD (PHASE 1) |
RECONSTRUCTION OF EJIGBO - ISOKO BOUNDARY, OGURO ROAD (PHASE 1) |
1,508,580,333.04 |
2025 |
2025-04-17T14:26:22 |
2025-05-19T12:00 |
2025-05-21T09:00 |